Red Rock Central School Lamberton, MN

130,000 SF, two-story new PK-12 school.

Construction Updates

Current Updates: Building Exterior

  • The Kalwall system (windows in the gym) are scheduled to start installs Monday 2.12.24
  • C&D upper/lower we are currently wrapping up drywall, framing & taping
  • Exterior window installs are on-going. C&D windows should be complete by 2.16.24
  • Miscellaneous painting will start next week in several area’s
  • Steel Erection is at 90% complete
  • Mech, Elec & plumbing work is on-going in each area of the school
1st grade classroom
5th and 6th grade
Auditorium
Auditorium
Choir and Band Room
Corridor
Fitness Room
Bathroom
Kitchen Area
Learning Stair
Lockeroom
Lockeroom
Main Commons
Main Gym
Main Office
Math and Social Studies
Media Center
Receiving Dock
Wood Shop
Wood Shop

Upcoming Work: Building Exterior

  • Slab on Grade – All of our concrete is poured except for the auditorium which we are holding off until late February or early March.
  • Aluminum entrances: select entrances will be installed in February
  • We are installing the remaining stairs on site by February 26th

Weather

  • Construction Days lost to Weather This Month: 0 in January
  • Total Construction Days lost to Weather: 8 total