130,000 SF, two-story new PK-12 school.
Construction Updates
Current Updates: Building Exterior
- The Kalwall system (windows in the gym) are scheduled to start installs Monday 2.12.24
- C&D upper/lower we are currently wrapping up drywall, framing & taping
- Exterior window installs are on-going. C&D windows should be complete by 2.16.24
- Miscellaneous painting will start next week in several area’s
- Steel Erection is at 90% complete
- Mech, Elec & plumbing work is on-going in each area of the school
Upcoming Work: Building Exterior
- Slab on Grade – All of our concrete is poured except for the auditorium which we are holding off until late February or early March.
- Aluminum entrances: select entrances will be installed in February
- We are installing the remaining stairs on site by February 26th
Weather
- Construction Days lost to Weather This Month: 0 in January
- Total Construction Days lost to Weather: 8 total